Long Island Construction Law Obtains Contractor Victory in Wrongful Termination

What does Long Island construction law say about terminating construction agreements? Despite the increasingly common use of arbitration in construction agreements, the New York Supreme Court has clarified that owners cannot terminate their construction agreement and fail to follow requirements for termination without repercussions. A recent pre-arbitration victory by John Caravella, Esq. confirms that the court unwilling to waive terms contained for termination and remedial efforts post termination to cure will not suffice to transform a wrongful termination into a termination for cause.

In Schmitz Vs. Dezendorf Contracting, Petitioner’s (Goldberg-Schmitz) filed a Termination of Contract against Respondent (Dezendorf). Unfortunately, the only indication that the contractor knew about the Petitioners’ wish to terminate the contract for cause, was the fact that the architect was copied on the termination correspondence via Email. Therefore, the Court found that the Petitioners failed to follow the proper procedure for termination of the contract for cause and was set forth in § 14.2.2. As such, the termination was wrongful and § 14.2.3 required the Contractor to await payment until the work is finished did not apply.

 

CTA Button
 

Additionally, Petitioners have failed to submit evidence enough to establish that the parties intended for the claims provision requiring an initial determination by the contractor, § 15.1.2, to survive termination of the agreement. When it comes to Long Island construction law, the absence of specific language in the agreement indicating such intent, along with the inclusion of paragraph § 15.1.3, “Continuing Contract Performance,” seemed to underscore the presumption that Article 15 governing claims procedure was meant to apply only in the case of claims that arise while the contract is in effect. Therefore, the court found that the Respondent was not required to submit its claim to the architect prior to servicing its demand for arbitration.

John Caravella, Esq

The author, John Caravella Esq., is a construction attorney and formerly practicing project architect at The Law Office of John Caravella, P.C., representing architects, engineers, contractors, subcontractors, and owners in all phases of contract preparation, litigation, and arbitration across New York and Florida. He also serves as an arbitrator to the American Arbitration Association Construction Industry Panel. Mr. Caravella can be reached by email: John@LIConstructionLaw.com or (631) 608-1346.

The information provided on this website does not, and is not intended to, constitute legal advice; instead, all information, content, and materials available on this site are for general informational purposes only.  Readers of this website should contact their attorney to obtain advice with respect to any particular legal matter.  No reader, user, or browser of this site should act or refrain from acting on the basis of information on this site without first seeking legal advice from counsel in the relevant jurisdiction.  Only your individual attorney can provide assurances that the information contained herein – and your interpretation of it – is applicable or appropriate to your particular situation.  Use of, and access to, this website or any of the links or resources contained within the site do not create an attorney-client relationship between the reader, user, or browser and website authors, contributors, contributing law firms, or committee members and their respective employers.