Real Estate Services

New York Offices

MANHATTAN
11 Penn Plaza
5th Floor
New York, NY 10001
CALL
(917) 508-7769

UNIONDALE
626 RexCorp Plaza
6th Floor West Tower
Uniondale, New York 11556
CALL
(516) 462-7051


Construction Law Blog

Current Articles | RSS Feed RSS Feed

Defects By Design; Who is Liable for Bad Plans and Specs

  
  
  
  
  

     Construction is fraught with countless risks, from weather conditions, labor strikes, material unavailability, subsurface conditions, and from inaccurate plans and specifications, among others. Each has the potential to delay the project, cause increased completion costs, and increase the likelihood of disputes, liens, or litigation. Problems stemming from inaccurate plans and specs can quickly become the problems of others beyond just the design professional itself.

Faulty Plans

     It is undisputed that New York construction law imposes primary responsibility for plan and specification accuracy on the design professional itself. The design professional is required to use the degree of skill, knowledge, and judgment ordinarily used by other design professionals in the same geographic area.

     However the issue becomes more complicated where an owner has its architect prepare plans and specifications, and provides them to its contractor. As between the owner and the contractor, it is the owner who bears the risk of any deficiencies in the architecturals. This allocation of risk, known as the Spearin Doctrine, stems from the 1918 United States Supreme Court matter of U.S. v. Spearin, 54 Ct. Cl. 187, 248 U.S. 132.[1]

     In Spearin, the contractor was constructing a federal dry dock, with the plans and specifications provided by the owner. The plans failed to show a dam, which later failed and caused the dry dock to flood. The Court found that in issuing the plans, the owner extended an implied warranty to the contractor, warranting that the plans and specifications, if complied with, would be adequate for its intended purpose.[2]

     Where a contractor has reason to believe that some error, oversight, or defect exists in the plans and specifications provided to it by the owner, the contractor should notify the owner promptly of these claims (preferably in writing). Where such a defect is not noticed by any party until after bidding, the plans would then arguably be defective under the Spearin Doctrine.

     The contractor under New York construction law is charged only with constructing the project in conformance with the architecturals, and to point out to the owner any deficiencies in the provided architecturals that it discovers. This does not arise to the contractor having responsibility for any deficiencies it fails to discover.

     Your comments and future article topic suggestions are invited in the field below.

John Caravella construction lawyerThe author, John Caravella Esq., is a construction attorney and formerly practicing project architect at The Law Office of John Caravella, P.C., representing architects, engineers, contractors, subcontractors, and owners in all phases of contract preparation, litigation, and arbitration across New York and Florida. He also serves as an arbitrator to the American Arbitration Association Construction Industry Panel. Mr. Caravella can be reached by email: John@LIConstructionLaw.com or (631) 608–1356 or (516) 462-7051.


textformat-leading2p-alignleft

[1] Not all states follow the Spearin Doctrine,

[2] the Court also found that this warranty could not be avoided by requiring contractor to examine the site, plans, and specifications prior to entering the contract. As such, contractors can typically recover extra costs incurred to overcome design defects

This is a general information article and should not be construed as legal advice or a legal opinion.  Readers are encouraged to seek counsel from a construction lawyer for advice on a particular circumstance.

Comments

In the hypothetical scenario you laid out, would the owner then have a claim against the design professional - assuming that the professional provided the plans to that owner?
Posted @ Wednesday, November 09, 2011 5:43 PM by Dick Frye
John, This an interesting and important topic. It could lead to lengthy discussion in a multitude of directions. But before venturing further into the concepts at play, I wonder if you might clarify what appears to me to be a critical flaw in the facts of the Spearin Case? 
You state that the contract documents failed to show a dam, then go on to say that the dam failed. These are conflicting statements which logically can not both be true.  
Surely there are many elements of this case which you have left out. There are many ways to employ architects and engineers for design services, it seems to me critical to know exactly what this owner contracted for. While an architect typically assumes a lead role in the process, an engineer (or engineers) would take on the responsibility for design of civil structures, including a dry dock. 
Regards, 
JS 
Posted @ Thursday, February 09, 2012 8:16 AM by John Sweeney
John - 
 
Thank you for your comments. Yes, the length of the article requires substantial condensing of facts, but the statements relating to the dam are neither a critical fraw nor are they conflicting statements. 
 
The issue was that a damn in close proximity to the work failed, and this dam failed to appear on the drawings. This failure to show a nearby dam which could fail and destroy the work was considered the very risk of faulty plans and specifications that needed to be clarified. who does bear the risk of faulty plans or specifications? what risks should which party bear? 
 
The contractors responsibility is to build (the project) according to the approved plans and specifications. 
 
The design professional is required to use the degree of skill, knowledge, and judgment ordinarily used by other designers in the same geographic area. 
 
 
 
Posted @ Friday, February 10, 2012 9:55 AM by John Caravella
Post Comment
Name
 *
Email
 *
Website (optional)
Comment
 *

Allowed tags: <a> link, <b> bold, <i> italics

Subscribe by Email

Your email:

Follow Me

Categories